E3 partnered with Glen Rose Medical Center to deliver a comprehensive facility upgrade focused on energy efficiency, system reliability, and long-term operational savings. The fully engineered project was executed through a seamless design-build approach to minimize disruption to patient care while modernizing key infrastructure components.
HVAC Upgrades
- Replaced (2) air-cooled chillers and associated chilled water pumps
- Replaced (4) rooftop air handlers and refurbished (1) additional unit
- Replaced (2) DX rooftop air handlers and (5) packaged rooftop HVAC units
- Installed (21) VAV boxes serving Med-Surg patient areas
- Replaced (2) hot water boilers and associated hot water pumps
- Upgraded (2) domestic hot water heaters and pumps
Building Controls
- Complete conversion from pneumatic to direct digital controls (DDC) system
Electrical Improvements
- Upgraded one electrical panel to support new equipment
Lighting Improvements
- Retrofitted over 1,300 interior and exterior fixtures to LED technology
Results
- Significantly improved energy efficiency and reduced operational costs
- Enhanced patient comfort and indoor environmental quality
- Increased system reliability and ease of maintenance