• MARKET : Healthcare
  • PROJECT SCOPE : Comprehensive HVAC, Controls and LED Retrofit
  • CONTRACT AMOUNT : $3,914,460
  • ANNUAL SAVINGS :
  • VISUALIZATION :
Comprehensive HVAC, Controls and LED Retrofit

GLEN ROSE MEDICAL CENTER

E3 partnered with Glen Rose Medical Center to deliver a comprehensive facility upgrade focused on energy efficiency, system reliability, and long-term operational savings. The fully engineered project was executed through a seamless design-build approach to minimize disruption to patient care while modernizing key infrastructure components.

HVAC Upgrades

  • Replaced (2) air-cooled chillers and associated chilled water pumps
  • Replaced (4) rooftop air handlers and refurbished (1) additional unit
  • Replaced (2) DX rooftop air handlers and (5) packaged rooftop HVAC units
  • Installed (21) VAV boxes serving Med-Surg patient areas
  • Replaced (2) hot water boilers and associated hot water pumps
  • Upgraded (2) domestic hot water heaters and pumps

Building Controls

  • Complete conversion from pneumatic to direct digital controls (DDC) system

Electrical Improvements

  • Upgraded one electrical panel to support new equipment

Lighting Improvements

  • Retrofitted over 1,300 interior and exterior fixtures to LED technology

Results

  • Significantly improved energy efficiency and reduced operational costs
  • Enhanced patient comfort and indoor environmental quality
  • Increased system reliability and ease of maintenance